Making a retaining wall that lasts is mostly about the parts you cannot see when it is finished. Here is how a builder does it, step by step, and where DIY walls usually go wrong.
1. Site assessment
Measure the levels, check the soil, find services such as stormwater, sewer, gas and power, and look at access for machines and spoil removal. Decide what the wall must hold back, including any driveway, fence or building above it.
2. Design and approval
Choose the wall type and get engineering and council approval where needed. Low walls up to 600mm can be exempt in NSW if they meet the rules. See council approval.
3. Set-out
Peg out the wall line and heights, check boundaries, and agree drainage outlet points.
4. Excavation
Cut the slope back to allow room for the wall, footings and drainage zone. Remove spoil from site. On steep sites, excavate in stages so the cut stays stable.
5. Footings or base
- Sleeper walls: post holes to the designed depth, posts set plumb in concrete.
- Block and concrete walls: a reinforced concrete strip footing.
- Gabion and segmental walls: a compacted crushed rock base.
6. Build the wall
Install sleepers, lay blocks, place gabion baskets or fix reinforcement and pour, checking level and alignment as you go.
7. Drainage
Lay ag pipe at the base behind the wall, falling to the outlet. Line the drainage zone with geofabric and backfill with clean aggregate. Install weep holes where the wall type needs them.
8. Backfill and compaction
Backfill in layers, compacting each one. Dumping all the fill at once and compacting the top only leads to settlement and extra pressure.
9. Finishing
Capping, surface drainage at the top of the wall, topsoil and planting, and any fence on top.
Where DIY walls go wrong
- Posts too shallow for the height.
- No drainage, or ag pipe with nowhere to discharge.
- Backfilling with clay instead of aggregate.
- Building taller than allowed without approval or engineering.
- Digging near services or the neighbour's footings.
DIY can suit a low garden edge. For anything that retains real soil, or sits near a boundary, driveway or building, a licensed builder is the safer choice. See our cost guide.
Get your free retaining wall quote
Talk directly with Constantine, the builder. Free site assessment and an itemised quote within 24 hours.
Request Free QuotationFrequently Asked Questions
How long does it take to build a retaining wall?
A typical residential wall takes several days to a couple of weeks, depending on length, height, access and excavation. Approvals can add weeks before work starts.
What goes behind a retaining wall?
An ag pipe at the base, clean drainage aggregate wrapped in geofabric, and compacted backfill.
Can I build my own retaining wall?
Low garden walls, yes. Walls retaining real soil, over 600mm, or near boundaries, driveways or buildings should be built by a licensed builder.